Tuesday, November 25, 2008

Waterfall Or Linear Sequential Model

The oldest of these, and the best known, is the waterfall: a sequence of stages in which the output of each stage becomes the input for the next. These stages can be characterized and divided up in different ways, including the following:

Project planning, feasibility study: Establishes a high-level view of the intended project and determines its goals.

This is also known as Classic Life Cycle Model (or) Linear Sequential Model (or) Waterfall Method. This model has the following activities.

Systems analysis, requirements definition: Refines project goals into defined functions and operation of the intended application, analyzes end-user information needs.

Systems design: Describes desired features and operations in detail, including screen layouts, business rules, process diagrams, pseudo code and other documentation.

Implementation: The real code is written here.

Integration and testing: Brings all the pieces together into a special testing environment, then checks for errors, bugs and interoperability.

Acceptance, installation, deployment: The final stage of initial development, where the software is put into production and runs actual business.

Maintenance: What happens during the rest of the software's life: changes, correction, additions and moves to a different computing platform and more? This, the least glamorous and perhaps most important step of all, goes on seemingly forever.

1. System/Information Engineering and Modeling

As software is always of a large system (or business), work begins by establishing the requirements for all system elements and then allocating some subset of these requirements to software. This system view is essential when the software must interface with other elements such as hardware, people and other resources. System is the basic and very critical requirement for the existence of software in any entity. So if the system is not in place, the system should be engineered and put in place. In some cases, to extract the maximum output, the system should be re-engineered and spruced up. Once the ideal system is engineered or tuned, the development team studies the software requirement for the system.

2. Software Requirement Analysis

This process is also known as feasibility study. In this phase, the development team visits the customer and studies their system. They investigate the need for possible software automation in the given system. By the end of the feasibility study, the team furnishes a document that holds the different specific recommendations for the candidate system. It also includes the personnel assignments, costs, project schedule, target dates etc.... The requirement gathering process is intensified and focused specially on software. To understand the nature of the program(s) to be built, the system engineer or "Analyst" must understand the information domain for the software, as well as required function, behavior, performance and interfacing. The essential purpose of this phase is to find the need and to define the problem that needs to be solved.

3. System Analysis and Design

In this phase, the software development process, the software's overall structure and its nuances are defined. In terms of the client/server technology, the number of tiers needed for the package architecture, the database design, the data structure design etc... are all defined in this phase. A software development model is thus created. Analysis and Design are very crucial in the whole development cycle. Any glitch in the design phase could be very expensive to solve in the later stage of the software development. Much care is taken during this phase. The logical system of the product is developed in this phase.

4. Code Generation

The design must be translated into a machine-readable form. The code generation step performs this task. If the design is performed in a detailed manner, code generation can be accomplished without much complication. Programming tools like compilers, interpreters, debuggers etc... are used to generate the code. Different high level programming languages like C, C++, Pascal, Java are used for coding. With respect to the type of application, the right programming language is chosen.

5. Testing

Once the code is generated, the software program testing begins. Different testing methodologies are available to unravel the bugs that were committed during the previous phases. Different testing tools and methodologies are already available. Some companies build their own testing tools that are tailor made for their own development operations.

6. Maintenance
The software will definitely undergo change once it is delivered to the customer. There can be many reasons for this change to occur. Change could happen because of some unexpected input values into the system. In addition, the changes in the system could directly affect the software operations. The software should be developed to accommodate changes that could happen during the post implementation period.

No comments:

Post a Comment